Project Schedule
| Stevensville Wye |
2-Apr-08 |
15-Jun-09 |
| Topsoil |
02-Apr-08* |
8-Feb-08 |
| Excavation |
complete |
| Special Borrow |
complete |
| Base Gravel |
|
30-Aug-08 |
| Electrical |
|
30-Aug-08 |
| Curb & Gutter |
18-Aug-08* |
15-Sep-08 |
| Grade S Plantmix |
8-Sep-08* |
30-Sep-08 |
| Grade B Plantmix |
30-Sep-08* |
31-Oct-08 |
| Signs |
06-Oct-08* |
14-Nov-08 |
| Preliminary Striping |
27-Oct-08* |
29-Oct-08 |
| Seal & Cover |
08-Jun-09* |
10-Jun-09 |
| Final Striping |
11-Jun-09* |
15-Jun-09 |
| Storm Drain |
complete |
| Mainline Storm Drain Pipe/Manholes |
complete |
| Siphons/Culvert Pipe |
complete |
| Laterals/Inlets |
complete |
| Approach Pipes |
|
31-Aug-08 |
| Arch Pipe |
complete |
|
|
|
| Bridges |
07-Apr-08 |
10-Oct-08 |
| Phase 1 Work |
7-Apr-08 |
26-Jun-08 |
| McCalla Creek Bridge |
complete |
| Piling |
complete |
| Class DD Concrete |
complete |
| Set MT-28 Prestressed Beams |
complete |
| Class SD Concrete |
complete |
| Switch Traffic |
complete |
| Remove Existing Structure |
complete |
| Kootenai Creek Bridge |
complete |
| Class DD Concrete |
complete |
| Piling |
complete |
| Set MT-28 Prestressed Beams |
complete |
| Class SD Concrete |
complete |
| Switch Traffic |
complete |
| Remove Existing Structure |
complete |
| Phase 2 Work |
30-Jun-08 |
10-Oct-08 |
| McCalla Creek Bridge |
30-Jun-08 |
1-Sep-08 |
| Piling |
complete |
| Class DD Concrete |
08-Jul-08* |
20-Aug-08 |
| Set MT-28 Prestressed Beams |
22-Jul-08* |
25-Jul-08 |
| Class SD Concrete |
23-Jul-08* |
25-Aug-08 |
| Remove Sheet Pile Shoring |
26-Aug-08* |
26-Aug-08 |
| De-Mobilization 1 1 0% 205 |
01-Sep-08* |
1-Sep-08 |
| Kootenai Creek Bridge |
8-Jul-08 |
10-Oct-08 |
| Piling |
complete |
| Class DD Concrete |
14-Jul-08* |
02-Sep-08 |
| Set MT-28 Prestressed Beams |
complete |
| Class SD Concrete |
29-Jul-08* |
22-Aug-08 |
| Remove Sheet Pile Shoring |
25-Aug-08* |
25-Aug-08 |
| De-Mobilization |
22-Sep-08* |
10-Oct-08 |
The daily News
4/7/08 Work has begun between McCalla and Stevi Wye