Project Schedule

Stevensville Wye 2-Apr-08 15-Jun-09
Topsoil 02-Apr-08* 8-Feb-08
Excavation complete
Special Borrow complete
Base Gravel   30-Aug-08
Electrical   30-Aug-08
Curb & Gutter 18-Aug-08* 15-Sep-08
Grade S Plantmix 8-Sep-08* 30-Sep-08
Grade B Plantmix 30-Sep-08* 31-Oct-08
Signs 06-Oct-08* 14-Nov-08
Preliminary Striping 27-Oct-08* 29-Oct-08
Seal & Cover 08-Jun-09* 10-Jun-09
Final Striping 11-Jun-09* 15-Jun-09
Storm Drain complete
Mainline Storm Drain Pipe/Manholes complete
Siphons/Culvert Pipe complete
Laterals/Inlets complete
Approach Pipes   31-Aug-08
Arch Pipe complete



Bridges 07-Apr-08 10-Oct-08
Phase 1 Work 7-Apr-08 26-Jun-08
McCalla Creek Bridge complete
Piling complete
Class DD Concrete complete
Set MT-28 Prestressed Beams complete
Class SD Concrete complete
Switch Traffic complete
Remove Existing Structure complete
Kootenai Creek Bridge complete
Class DD Concrete complete
Piling complete
Set MT-28 Prestressed Beams complete
Class SD Concrete complete
Switch Traffic complete
Remove Existing Structure complete
Phase 2 Work 30-Jun-08 10-Oct-08
McCalla Creek Bridge 30-Jun-08 1-Sep-08
Piling complete
Class DD Concrete 08-Jul-08* 20-Aug-08
Set MT-28 Prestressed Beams 22-Jul-08* 25-Jul-08
Class SD Concrete 23-Jul-08* 25-Aug-08
Remove Sheet Pile Shoring 26-Aug-08* 26-Aug-08
De-Mobilization 1 1 0% 205 01-Sep-08* 1-Sep-08
Kootenai Creek Bridge 8-Jul-08 10-Oct-08
Piling complete
Class DD Concrete 14-Jul-08* 02-Sep-08
Set MT-28 Prestressed Beams complete
Class SD Concrete 29-Jul-08* 22-Aug-08
Remove Sheet Pile Shoring 25-Aug-08* 25-Aug-08
De-Mobilization 22-Sep-08* 10-Oct-08

The daily News

4/7/08 Work has begun between McCalla and Stevi Wye